VICT's Phase 3A expansion completed, box handling capacity up 30pc
SEAPORT SUPPLY CHAIN LTD Published On£º2024-03-07 16:52:19

PHILIPPINES' International Container Terminal Services, Inc (ICTSI) has completed expansion of Phase 3A of its automated Victoria International Container Terminal (VICT) in Melbourne, Australia.

Phase 3A of the two stage AUD235 million (US$153 million) expansion project increases VICT's capacity by 30 per cent to 1.25 million TEU and enables the terminal to handle neo-Panama vessels, reports UK's Seatrade Maritime News.

"This additional investment redefines the Port of Melbourne's landscape, setting new standards for operational efficiency and capacity. VICT can now accommodate the largest container vessels calling Australia - the neo-Panamax giants - solidifying the Port of Melbourne's position as Australia's number one container port," said Enrique K Razon Jr, ICTSI chairman and president.

Philippines President Ferdinand R Marcos Jr, together with First Lady Liza Araneta-Marcos and Mr Razon Jr, unveiled the plate to mark the inauguration of the VICT's Phase 3 expansion. The remote ceremony was held at The Ritz-Carlton in Melbourne.

"Being the only fully automated container terminal in the Southern hemisphere is truly a feat worthy of admiration," President Marcos said. "This expansion that we are seeing today is a clear sign that Filipino companies can compete at some of the most advanced economies in the world. And in the case of VICT, they are in it for the long haul. We look forward to VICT's continued success and growth," he added.

VICT also acquired two automated ship-to-shore (STS) cranes, six auto container carriers (ACC) and six auto stacking cranes (ASC) as part of Phase 3A. The ASCs have been operational since December 2023, supporting the increased yard capacity. The STS cranes, which have a reach of twenty-two containers across and currently the largest port equipment in Australia, are now operational.

Phase 3B is scheduled to be completed in 2026 and will include the acquisition of another automated STS crane, three ACCs, four ASCs, and construction of two additional storage blocks.

Address£º27/F, Shenhua Commercial Building, Jiabin Road 2018, Luohu District, Shenzhen, China
Head line£º(86)755-82294666(switchboard)
Fax£º0086-755-82352388
SEAPORT SUPPLY CHAIN LTD.©Copyright

ÔÁICP±¸09155187ºÅ-1